Enviro Infra Engineers Limited has announced that its step-down subsidiary, Suyog Urja Limited, has secured an EPC turnkey contract worth ₹189.99 Crore (excluding GST). The contract is for the development of a 180 MW NTPC Wind Power Project at Parli, Maharashtra. The project involves comprehensive works including WTG foundation, balance of plant, and 33kV transmission line construction, with execution expected by March 31, 2027.
Major EPC Contract Secured
Enviro Infra Engineers Limited, through its step-down subsidiary Suyog Urja Limited (SUL), has been awarded a significant EPC (Engineering, Procurement, and Construction) turnkey contract valued at ₹189.99 Crore (excluding GST). The contract was secured from TATA POWER RENEWABLE ENERGY LIMITED and pertains to the execution of works for a 180 MW NTPC Wind Power Project located in Parli, Maharashtra.
Scope of Work and Project Details
The comprehensive scope of the contract includes:
- Foundation Works: Supply of reinforcement steel and Geotech for Wind Turbine Generator (WTG) foundations.
- Balance of Plant (BoP): Development of a fully equipped 39-acre secure storage yard, coordination of Right of Way (ROW) for material transport, and construction of permanent and temporary roads, pathways, and crane pads.
- Transmission Line: Construction and commissioning of 33kV Transmission Line Works.
The contract is with a domestic entity and the execution is slated to be completed by March 31, 2027.
Company’s Confirmation
The company confirmed receiving the intimation from SUL on September 8, 2026, at 11:24 A.M. The announcement highlights Enviro Infra Engineers’ growing presence and capabilities in the renewable energy infrastructure sector.