Schneider Electric Infrastructure Limited’s Board of Directors has approved a substantial expansion of its manufacturing capacity at the Kolkata Medium Voltage Components (KMVC) facility. The company will increase Vacuum Interrupter capacity by 50%, from 250,000 to 375,000 units per annum, and introduce a new Breaker capacity of 18,000 units per annum. This expansion, requiring an investment of INR 211 crore, is targeted for completion by the end of FY 2028-29.
Capacity Expansion Approved for KMVC Facility
Schneider Electric Infrastructure Limited has announced a significant capacity enhancement at its Kolkata Medium Voltage Components (KMVC) facility. The Board of Directors, in a meeting held on October 29, 2026, approved the plan to increase the production capacity for Vacuum Interrupters and Breakers. This move is expected to support the company’s growth objectives, including export plans and technology upgrades.
Key Details of Capacity Enhancement
The approved revision aims to further enhance the Vacuum Interrupter capacity from the existing 250,000 units per annum to 375,000 units per annum. Additionally, the company will introduce a new production line for Breaker capacity, adding 18,000 units per annum. These upgrades represent a material increase in the company’s manufacturing capabilities.
Investment and Timeline
To support this expansion, Schneider Electric plans to invest INR 211 crore. The financing for this investment will be sourced through internal accruals and/or external borrowings. The proposed capacity is slated to be added and fully operational by the end of FY 2028-29. The rationale behind this investment is to support the company’s capacity augmentation requirements, fuel export growth plans, and implement technology upgradation initiatives.
The existing capacity for Vacuum Interrupters was reported at 250k units per annum, with the capacity being installed in phases. This proposed addition aims to meet growing market demand and strengthen the company’s competitive position.
Source: BSE