NTPC Renewable Energy Limited, a subsidiary of the NTPC group, has successfully commissioned the 90 MW seventh part capacity of its 1200 MW Khavda-II Solar PV Project in Gujarat. Effective April 25, 2026, this expansion contributes to the group’s growing renewable energy portfolio. With this latest addition, the total installed capacity for the NTPC group has reached 89,705 MW, while the commercial capacity now stands at 88,625 MW.
Boosting Renewable Energy Capacity
As part of its ongoing commitment to sustainable energy, NTPC Limited has announced the successful operationalization of a new 90 MW solar power unit. This capacity represents the seventh part of the larger 1200 MW Khavda-II Solar PV Project located in the state of Gujarat. The project is managed by NTPC Renewable Energy Limited, a step-down subsidiary operating under the parent company’s green energy arm.
Strategic Growth Milestones
The facility officially entered commercial operation on April 25, 2026. This milestone is a significant step in the company’s broader efforts to expand its solar infrastructure. Following this commissioning, the NTPC group now manages a total installed capacity of 89,705 MW across its various power generation segments. Furthermore, the commercial capacity of the NTPC group has scaled to 88,625 MW, reflecting the company’s steady progress in enhancing its national power output.
Impact on Green Energy Subsidiary
NTPC Green Energy Limited continues to play a pivotal role in the group’s transition toward cleaner energy. With the integration of this latest 90 MW project, the total installed capacity of the NTPC Green Energy Limited group has increased to 10,453.90 MW. This growth underscores the company’s strategic focus on scaling up its renewable energy footprints to meet rising energy demands.
Source: BSE