KNR Constructions has announced the receipt of the Completion Certificate for the Construction of Elevated Highway along Avinashi Road in Coimbatore. The project connects Goldwins to Uppilipalayam (Km 147/100 – 157/200 of SHU-52) in Tamil Nadu, executed under the Engineering, Procurement, and Construction (EPC) Mode. The project cost was ₹1,180.00 crore.
Avinashi Road Project Achievement
KNR Constructions has successfully completed the Construction of Elevated Highway along Avinashi Road in Coimbatore. The company has received the official Completion Certificate.
Project Details
The project scope included the construction of an elevated highway connecting Goldwins to Uppilipalayam (Km 147/100 – 157/200 of SHU-52) in Tamil Nadu. It was executed under the Engineering, Procurement, and Construction (EPC) Mode.
Project Cost: ₹1,180.00 crore (including GST)
Appointed Date: 07-Sept-2020
Construction Period: 48 Months
Scheduled Completion Date: 06-Sept-2024
Revised Scheduled Completion Date: 07-Dec-2025
Date of Completion Certificate: 08-Oct-2025
Source: BSE