NTPC Green Energy Limited (NGEL), a subsidiary of NTPC, has declared the commercial operation of a part capacity of 9.9 MW (Wind). This capacity is part of a larger 92.4 MW wind project in Bhuj, Gujarat, through Ayana Renewable Power Four Private Limited. This addition increases NGEL’s total installed capacity, demonstrating progress in renewable energy initiatives.
Wind Energy Project Update
NTPC Green Energy Limited (NGEL), a subsidiary of NTPC Limited, has announced the commencement of commercial operations for a portion of its wind energy project. This announcement was made on October 23, 2025.
Capacity and Location
The newly operational capacity is 9.9 MW of wind energy. This is part of a larger 92.4 MW wind project located in Bhuj, Gujarat. The project is operated through Ayana Renewable Power Four Private Limited, a subsidiary of Ayana Renewable Power Pvt. Ltd. which in turn is a wholly owned subsidiary of ONGC NTPC Green Private.
Impact on Total Capacity
With this addition, the commercial capacity of the NTPC Green Energy Limited Group now stands at 7553.675 MW. Following this addition, the total installed capacity of the NGEL Group has increased to 7563.575 MW. This reflects the company’s ongoing efforts to expand its renewable energy portfolio.
NTPC Group Total Capacity
Including this addition from NGEL, the total installed and commercial capacity of the NTPC group now stands at 84,049 MW. This milestone underlines NTPC’s commitment to increasing its green energy footprint.