NLC India has announced the commencement of commercial operation for a portion of its 300 MW solar power project, adding 106 MW of capacity. This follows the earlier commissioning of 52.83 MW. The project is located in Barsingsar, Bikaner, Rajasthan. With this addition, the total declared capacity on commercial operation stands at 158.83 MW out of the 300 MW project.
Solar Project Update
NLC India has announced that the second phase of its 300 MW Solar Power Project is now commercially operational. This phase adds 106 MW to the company’s operational capacity. The project is located at Barsingsar, Distt. Bikaner, Rajasthan.
Operational Capacity
The commissioning certificate for this phase has been received from Rajasthan Renewable Energy Corporation Limited on November 2nd, 2025.
Previously, a capacity of 52.83 MW had already been declared on commercial operation, effective August 26th, 2025. The total declared capacity on commercial operation now stands at 158.83 MW out of the total 300 MW capacity of the project.
Source: BSE