Hindustan Construction Company (HCC) Q3 FY26 Results and Operations Update Presentation

Hindustan Construction Company (HCC) released its Q3 FY26 investor presentation detailing financial results and key operational milestones. Standalone turnover was ₹921.8 Cr, while EBITDA margin improved slightly to 15.2%. The company secured new JV orders worth ₹1,478 crore, secured a robust bid pipeline of ₹53,820 Cr, and reported strong progress across major ongoing projects like the Indore Metro and various hydro-electric power projects.

Q3 FY26 Financial Performance Highlights

HCC provided a detailed overview of its financial performance for the quarter ending December 31, 2025 (Q3 FY26). Standalone turnover stood at ₹921.8 Cr, compared to ₹1,002.1 Cr in Q3 FY25, representing an 8.0% drop year-on-year. However, standalone EBITDA margin showed resilience, expanding to 15.2% from 14.7% in the previous year’s corresponding quarter. Standalone Net Profit saw a significant turnaround, recording ₹85.9 Cr against a loss of (₹216.4) Cr in Q3 FY25, aided by exceptional income of ₹37.8 Cr.

Consolidated Results Snapshot

On a consolidated basis, Total Income decreased by 9.8% to ₹961.5 Cr. Consolidated EBITDA (excluding other income) was ₹67.2 Cr, a significant improvement from the negative EBITDA of (₹30.5) Cr in Q3 FY25. The company reported a consolidated Profit/(loss) after tax of ₹8.1 Cr for the quarter.

Order Book and Business Momentum

The Order Backlog remains healthy at ₹13,148 Cr. The business line-wise distribution shows 65% reliance on Water projects, followed by 19% in Transport. Geographically, 25% of the order book is concentrated in Maharashtra.

Key business updates include securing two new joint venture orders from the Northern Frontier Railways, aggregating ₹1,478 crore (HCC holding a 65% stake). The bid submitted and under evaluation pipeline is strong at approximately ₹53,820 Cr. Furthermore, the recent ₹1,000 crore Rights Issue was subscribed by ~200%.

Significant Deleveraging and Financial Progress

The company highlighted significant progress in debt reduction. HCC planned an additional ₹876 Cr repayment in Q4, building on ₹680 Cr prepayments made in FY26, driving the substantial debt reduction target to approximately ₹1950 Cr. Additionally, the HCC Corporate Guarantee on debt of Prolific Resolution Pvt. Ltd. was successfully reduced from 100% to 20%.

Key Project Operations Updates

Metro Projects

  • Patna Metro Rail Project (Packages 05 & 06): Commencement was inaugurated by the Chief Minister of Bihar, Shri Nitish Kumar.
  • Indore Metro Rail Project: Piling works are active across all five stations, with station excavation underway at the Airport and Rajwada stations. Trial Ring Assembly was also showcased.

Hydro Power Projects

  • Vishnugad-Pipalkoti HEP (4×111 MW): A significant portion of dam concrete works is achieved, and 8.5 km of the planned 12.1 km Head Race Tunnel (HRT) has been excavated using the TBM.
  • Tehri PSP (4×250 MW): The powerhouse construction is progressing well, as indicated by overview images.
  • Bhivpuri PSP (3×333.33 MW): Lower Reservoir Excavation is actively in progress.
  • Tapovan Vishnugad HEP (4×130 MW): Tunnel excavation activity is ongoing at Face 4 and Face 5.

Other Infrastructure

  • Agardanda Creek Bridge: Piling works at Navigation Span P51 and Segment Casting activities are advancing in line with schedules.
  • Fast Reactor Fuel Cycle Facility (FRFCF): Construction update shows ongoing work on Block 6 and Block 7 structures.

Source: BSE

Previous Article

UNIMECH Aerospace and Manufacturing Limited Statement of Deviation in IPO Fund Utilization for Q3 FY2025-26

Next Article

Electronics Mart India Limited Transcript of Earnings Conference Call for Q3 FY26