Enviro Infra Engineers Limited Secures ₹411 Crore Sewage Network and STP EPC Contract in Bihar

Enviro Infra Engineers Limited (EIEL) has secured a significant Letter of Acceptance (LOA) for a major infrastructure project in Bihar. The contract, awarded by the Bihar Urban Infrastructure Development Corporation, is valued at ₹411.08 Crores (including GST). The project involves the EPC of a 20 MLD Sewage Treatment Plant (STP) and a vast sewerage network, coupled with 5 years of Operation & Maintenance (O&M) in Aurangabad.

Major Contract Awarded to Enviro Infra Engineers

Enviro Infra Engineers Limited (EIEL) announced on 12th March, 2026, that it has received a Letter of Acceptance (LOA) for the execution of a crucial urban infrastructure project. The contract was awarded by the Bihar Urban Infrastructure Development Corporation Limited.

Project Details and Scope

The contract pertains to the Aurangabad Sewerage Network and STP Scheme under AMRUT 2.0. The scope of work is comprehensive and encompasses several key components:

  • Sewage Treatment Plant (STP): EPC work for a 20 MLD STP, including all appurtenant structures and allied works, managed via Scada systems.
  • Pumping Stations & Network: Construction of 8 Nos. pumping stations along with 5400 MTR rising main.
  • Sewerage Network: Laying of a substantial sewerage network covering 196 Km within Aurangabad Town, Bihar.
  • Nature of Contract: The award is under an Engineering, Procurement, and Construction (EPC) model, inclusive of a substantial Operation & Maintenance (O&M) component.

Financial Value and Timeline

The total consideration or size of the order is substantial, pegged at ₹411.08 Crores (including GST). This project is categorized as a Domestic award.

The execution timeline is structured as follows:

  1. The EPC phase is required to be completed within 15 months from the date of commencement.
  2. This will be followed by an Operation and Maintenance (O&M) period lasting for 5 years.

Related Party Disclosure

In compliance with disclosure requirements, EIEL confirmed that the promoter/promoter group/group companies have no interest in the entity that awarded this contract. Furthermore, the contract does not fall within related party transactions.

Source: BSE

Previous Article

ACME Solar Holdings Signs 450 MW/1800 MWh Power Purchase Agreements for Assured Peak Power Project

Next Article

Enviro Infra Engineers Limited Secures ₹411.08 Crore EPC Order for Aurangabad Sewerage Network