Chambal Fertilisers Project Completion Rescheduled to April 30, 2026

Chambal Fertilisers and Chemicals Limited has announced the rescheduling of the project completion date for its Technical Ammonium Nitrate plant. The new completion date is set for April 30, 2026. This revision is due to reasons attributable to the project’s EPC contractor. The plant is located at the Company’s existing site at Gadepan, District Kota, Rajasthan.

Project Completion Update

Chambal Fertilisers and Chemicals Limited has revised the expected completion date for its ongoing project to set up a plant for the manufacture of Technical Ammonium Nitrate, including a plant to manufacture Weak Nitric Acid (‘Project’).

Revised Completion Date

The date of completion of the Project has been rescheduled to April 30, 2026. The initial letters referenced were dated April 5, 2023, and January 22, 2025, regarding the execution of the project.

Reason for Delay

The rescheduling is due to reasons attributable to the EPC contractor involved in the project. The plant is located at the Company’s existing site at Gadepan, District Kota, Rajasthan.