Ather Energy has announced a revised timeline for the commencement of commercial operations at its Factory 3.0 in Chhatrapati Sambhajinagar, Maharashtra. Originally slated to begin in July 2026, the start date has been shifted to October 2026. This change is due to a delay in receiving the Environment Clearance approval, which was granted in September 2025. The company reaffirms its commitment to the successful completion of the factory.
Factory 3.0 Launch Pushed Back
Ather Energy has updated the commencement date for commercial operations at its new manufacturing facility, Factory 3.0, located in Chhatrapati Sambhajinagar (formerly Aurangabad), Maharashtra. The new timeline indicates that operations will begin in October 2026.
Reason for Delay
The company received the Environment Clearance approval in September 2025, which caused the delay. Previously, the commencement was projected for July 2026, as per the prospectus dated April 30, 2025. This shift reflects the adjustment in the project timeline.
Commitment to Completion
Despite the revised timeline, Ather Energy has confirmed its commitment to the successful completion of Factory 3.0. The company is actively working towards the facility’s opening and its contribution to the company’s manufacturing capabilities.
Source: BSE