ACME Solar announced its Q3 FY2026 results, showcasing a 53.9% increase in total revenue to INR 617 Cr. EBITDA rose by 57.2% to INR 564 Cr. The company commissioned 72 MW of wind projects, bringing the YTD total to 422 MW. Plans for BESS commissioning are now at ~2 GWh by Q4 FY26. Refinancing was achieved at 8.0% p.a. for 300 MW operational projects.

Financial Performance

ACME Solar reported strong financial results for Q3 FY26:

  • Total Revenue: Increased by 53.9% to INR 617 Cr (Q3 FY25: INR 401 Cr)
  • EBITDA: Up by 57.2% to INR 564 Cr (Q3 FY25: INR 359 Cr)
  • PAT: Increased to INR 114 Cr (Q3 FY25: INR 112 Cr)
  • Generation: Increased by 49.0% to 1,567 MUs (Q3 FY25: 1,052 MUs)

Operational Highlights

  • Partially commissioned 72 MW out of 100 MW wind project, bringing YTD commissioned capacity to 422 MW.
  • Won 130 MW round-the-clock project with Railway Energy Management Company Limited (REMC Limited).
  • PPAs signed for 450 MW projects, taking cumulative YTD PPA signed capacity to 1,050 MW and 550 MWh BESS.
  • BESS commissioning planned to be ~2 GWh by Q4 FY26.
  • Weighted average cost of debt for operational projects stands at 8.45%.
  • Latest refinancing at a rate of 8.0% p.a. for 300 MW operational projects.
  • Latest financing at an average rate of 8.9% p.a. for 450 MW under construction projects.

Project Updates

  • BESS commissioning ongoing at 3 project sites.
  • Connectivity inventory of ~7.5 GW available for upcoming bids.
  • 10,000+ acres of land acquired for under construction PPA signed projects.

Capacity Roadmap

ACME Solar is targeting a portfolio of 10 GW generation capacity and 20 GWh BESS capacity by 2030.

Source: BSE

Previous Article

Capri Global Capital Board Approves Global Debt Program & Q3 2026 Results

Next Article

Capri Global Capital Board Approves Global Medium Term Note Program and Q3 2026 Results