ACME Solar Holdings Limited (ASHL) announced the commissioning of the second phase of its major Battery Energy Storage System (BESS) project in Jaisalmer, Rajasthan. This phase adds 38 MW/82 MWh capacity to the overall 285 MW/600 MWh facility. The Commercial Operation Date (COD) for this specific Phase-II segment is set for March 05, 2026, marking a significant step in expanding the company’s energy storage infrastructure.
BESS Project Expansion Confirmed
ACME Solar Holdings Limited (“ASHL”), through its wholly owned subsidiary, ACME Suryodaya Private Limited, has successfully commissioned the second phase of its large-scale Battery Energy Storage System (BESS) Project located in Rajasthan. This announcement follows an earlier intimation dated February 25, 2026.
Capacity and Location Details
The newly commissioned segment represents Phase-II of the overall project. This phase contributes 38 MW/82 MWh of capacity. The total project, when fully implemented, will possess a capacity of 285 MW/600 MWh. The physical site for this major energy storage asset is situated at Village: Sanwara and Mehar Nagar, Tehsil-Pokhran, Dist: Jaisalmer, Rajasthan.
Commercial Operation Date Set
The crucial date for the commencement of commercial operations (COD) for the above-mentioned Phase-II has been officially established. The COD for this 38 MW/82 MWh segment is scheduled for March 05, 2026.
Conclusion of Disclosure
The company requested that the stock exchanges take this information on record as part of their ongoing regulatory disclosures. The filing was authorized by Rajesh Sodhi, Company Secretary and Compliance Officer, on March 03, 2026.