ACME Solar Holdings Limited (ASHL), via its subsidiary ACME Suryodaya Private Limited, has announced the commissioning of the fourth phase (Phase-IV) of its significant Battery Energy Storage System (BESS) project in Jaisalmer, Rajasthan. This phase adds 95 MW / 200.64 MWh capacity. The Commercial Operation Date (COD) for this phase is set as March 25, 2026. With this milestone, the subsidiary has now operationalized 171 MW / 361.14 MWh of the total planned capacity.
BESS Project Expansion Milestone Reached
ACME Solar Holdings Limited (“ASHL”) is pleased to confirm the successful commissioning of a significant segment of its Battery Energy Storage System (BESS) project situated in Jaisalmer, Rajasthan. The announcement, made on March 23, 2026, confirms that the fourth phase (Phase-IV) of the project has become operational.
Capacity Commissioned Details
The newly commissioned Phase-IV contributes 95 MW / 200.64 MWh to the overall system capacity. This project is being developed by ACME Suryodaya Private Limited, a wholly owned subsidiary of ASHL.
The Commercial Operation Date (COD) for this specific phase (Phase-IV) is officially set for March 25, 2026. The total planned capacity for the entire project located at Village: Sanwara and Mehar Nagar, Tehsil-Pokhran, is 285 MW / 601.904 MWh.
Cumulative Operational Capacity
Following the commissioning of Phase-IV, ACME Suryodaya Private Limited has achieved a substantial cumulative operational capacity of 171 MW / 361.14 MWh out of the total planned 285 MW / 601.904 MWh capacity. This achievement marks substantial progress towards completing the full-scale energy storage initiative.
Compliance and Next Steps
This disclosure serves as notification to the stock exchanges following previous intimations made on February 25, March 03, and March 11, 2026. The company requests that this operational update be taken on record.
Source: BSE