ACME Solar Holdings Limited announced that its subsidiary, ACME Eco Clean Energy Private Limited, has commissioned an additional 4 MW of capacity at its 100 MW wind power project located in Surendranagar, Gujarat. This latest addition brings the subsidiary’s total commissioned capacity for this specific project to 88 MW out of 100 MW. The successful commissioning was confirmed by GEDA and PGVCL officials, with the formal certificate anticipated shortly.
Wind Power Capacity Expansion Update
ACME Solar Holdings Limited has provided an important update regarding the ongoing development of its wind power portfolio. On March 19, 2026, the company confirmed that its subsidiary, ACME Eco Clean Energy Private Limited, successfully commissioned an additional 4 MW of capacity.
Project Details in Gujarat
This incremental capacity is part of the larger 100 MW wind power initiative being executed in the state of Gujarat. The specific site for this commissioning is Village: Titoda, Taluka: Sayla, Dist: Surendaranagar. This achievement follows a series of earlier intimations made by the company throughout late 2025 and early 2026 detailing project milestones.
Total Commissioned Capacity Achieved
With the successful integration of this 4 MW, ACME Eco Clean Energy Private Limited has now achieved a total commissioned capacity of 88 MW against the total planned capacity of 100 MW for this project. The process has been verified by both the Gujarat Energy Development Agency (“GEDA”) and Paschim Gujarat Vij Company Limited (“PGVCL”).
Source: BSE