Ceigall India Limited JV Emerges as L1 Bidder for Four MoRTH Highway Projects Valued at ₹2,149.62 Crore

Ceigall India Limited (CIL), in joint venture (JV) with Sushee Infra & Mining Limited (SIML), has emerged as the L1 bidder for four separate road construction tenders issued by the Ministry of Road Transport and Highways (MoRTH) on March 11, 2026. These projects, all under the Engineering Procurement Construction (EPC) mode on NH-913 in Arunachal Pradesh, aggregate to a total bid cost of Rs. 2,149.62 Crores. The individual projects have completion timelines ranging from 36 to 48 months plus a 5-year maintenance period.

L1 Bidder Status Confirmed for Major Highway Packages

Ceigall India Limited (CIL), holding a 74% share in the Joint Venture (JV) alongside Sushee Infra & Mining Limited (SIML, holding 26%), has successfully secured the L1 bidder position for multiple significant tenders from the Ministry of Road Transport and Highways (MoRTH) on March 11, 2026.

This announcement follows the previous intimation regarding one specific tender (ID: 2025_MoRTH_868241_1) for the Huri-Taliha section of NH-913, involving a bid cost of Rs. 521 Crores.

Cumulatively, CIL and SIML have emerged as L1 bidders for Four (4) projects, aggregating to a total bid cost of Rs. 2,149.62 crores.

Details of the Awarded EPC Contracts

All contracts are domestic and awarded under the Engineering Procurement Construction (EPC) mode. The construction period for these packages varies, ranging between 36 Months and 48 Months, followed by a mandatory 05 Year Maintenance Period for each contract.

Project Package Tender ID Bid Cost (Crore Rs.) Execution Time
Construction of road from km 0.000 to km 78.38 of Sarli-Huri section of NH-913 2025_MoRTH_8682251 611.10 36 Mth Construction + 05 Yr Maintenance
Construction of road from km 0.000 to km 55.725 of Huri-Taliha section of NH-913 (Initial Project) 2025_MoRTH_8682461 525.00 48 Mth Construction + 05 Yr Maintenance
Construction of road from km 55.725 to km 113.25 of Huri-Taliha section of NH-913 (Implied based on total) (Implied) (Not explicitly detailed for this specific segment in the summary table)
Construction of road from km 160.75 to km 209.90 of Huri-Taliha section of NH-913 2025_MoRTH_8682681 492.52 36 Mth Construction + 05 Yr Maintenance

Compliance and Transaction Status

The disclosure confirms that the promoter or promoter group companies do not have any interest in the awarding entity (MoRTH). Furthermore, these contracts are confirmed not to fall within related party transactions, implying they are conducted at “arm’s length”.

The company also notes that the information regarding these awards is being made public immediately after the financial bid openings on March 11, 2026, and is available on the company website, www.ceigall.com.

Source: BSE

Previous Article

NUVOCO VISTAS CORP. LTD. Clarifies Significant Surge in Trading Volume on March 11, 2026

Next Article

Shakti Pumps (India) Limited Clarifies No Material Information Behind Significant Trading Volume Increase