POWERGRID’s Committee of Directors has approved the procurement of cold spare Transformers & Reactors. This includes projects in 51st WRPC at an estimated cost of ₹401.88 crore, 28th NERPC at ₹166.33 crore, and 53rd SRPC at ₹345.78 crore. Implementation is scheduled within 30 months from the date of Investment Approval.
Project Approvals
POWERGRID has secured investment approval for the “Procurement of cold spare Transformers & Reactors” across multiple regions. The decisions were made during the Committee of Directors meeting held on January 20, 2026.
Key Project Details
The approved projects include:
- 51st WRPC: Procurement of cold spare Transformers & Reactors, estimated cost of ₹401.88 crore.
- 28th NERPC: Procurement of cold spare Transformers & Reactors, estimated cost of ₹166.33 crore.
- 53rd SRPC: Procurement of cold spare Transformers & Reactors, estimated cost of ₹345.78 crore.
Implementation Timeline
All the projects are scheduled for implementation within 30 months from the date of Investment Approval.
Source: BSE