Rail Vikas Nigam Limited (RVNL) has emerged as the lowest bidder (L1) for a project from Central Railway. The project involves the design, supply, erection, testing, and commissioning of traction substations and related infrastructure. This work is part of the company’s normal business operations. The project is aimed at meeting a 3000 MT loading target.
Central Railway Project Secured
Rail Vikas Nigam Limited (RVNL) has been identified as the lowest bidder (L1) for a significant project by Central Railway. The project focuses on upgrading railway infrastructure and enhancing traction systems.
Project Details and Scope
The project encompasses the design, supply, erection, testing, and commissioning of 220/132/55 KV Traction Substation, Sectioning Post (SPs), and Sub Sectioning Post (SSPs). These upgrades will be implemented in a 2×25 KV Traction System (Scott Connected Transformer) across the Daund-Solapur sections of Central Railway. The main objective is to meet a 3000 MT loading target on the EPC mode.
Project Timeline
The project is expected to be completed within 24 months.
Financial Details
The cost of the work is estimated at Rs 272,07,86,524.78/- including applicable taxes.
Source: BSE