KNR Constructions has announced the provisional completion of the six-lane highway project from Valanchery bypass to Kappirikkad section in Kerala. The project, executed under the Hybrid Annuity Mode, spans from Design Ch.298+500 to Ch.335+850. The completion date is effective from July 17, 2025. The bid project cost was ₹2140.00 crores.
Kerala Highway Project Achieves Completion
KNR Constructions Limited announced that they have received the Provisional Certificate of Completion for the six-laning project from Valanchery bypass to Kappirikkad section of NH-66 in Kerala. This project was executed under the Hybrid Annuity Mode.
Project Details and Costs
The highway spans from Design Ch.298+500 (Ex.km 304.250) to Design Ch.335+850 (Ex.km 349.260). The bid project cost amounted to ₹2140.00 crores.
Project Timeline
The appointed date for the construction was January 21, 2022, and the project was completed by July 17, 2025. The construction period included 1274 days with an extension of time (EOT) of 364 days.
Source: BSE